CompletedTransportation/HighwayRustam-Ambela- Daggar- Karakar-Barikot Road Ambela to GS Marble

The road section was desired to be widened and upgraded. It Starts near the Army Check Post outside Ambela Town and Ends near GS Marble Factory. The proposed road section is part of Mardan – Buner Swat Road.

Feasibility Studies and Detailed Design of Rustam-Ambela- Daggar- Karakar-Barikot Road Ambela to GS Marble (11Km) Section Including Bridge

M/s Indus Associated Consultants in a joint venture with another consultancy firm was awarded the subject project by PKHA through an open bidding process for Feasibility Studies and Detailed Design of Rustam-Ambela- Daggar- Karakar-Barikot Road Ambela to GS Marble (11Km) Section Including Bridge.

The road section was desired to be widened and upgraded. It Starts near the Army Check Post outside Ambela Town and Ends near GS Marble Factory. The proposed road section is part of Mardan – Buner Swat Road. The improved facility has resulted in saving travel time for traffic plying between Mardan and Swat. It has also improved marble trade and tourism in the area.

Scope of Work

Following was the scope of work for the subject assignment:

  1. Feasibility Study
  2. Topographic Survey
  3. Detailed Geometric & Pavement Design
  4. Soil & Geotechnical Investigation
  5. BOQ & Cost Estimate, Bidding Documents and Construction Drawings etc.

The Salient Features of the project are as under:

Client: PKHA
Project Length: 11 Km
Consultancy Cost: Rs. 9.54 million
Commencement Date: Oct, 2012
Completion Date: May, 2013
Status: Completed